This
system consists of one or more “PRIMARY LOOPS” with two or more transformers
connected on the loop. This system is typically most effective when two
services are available from the utility as shown in Figure 1.1-29. Each primary loop is operated such that one of the loop sectionalizing
switches is kept open to prevent parallel operation of the sources.
When
secondary unit substations are used, each transformer may have its own duplex
(2-load break switches with load side bus connection) sectionalizing switches
and primary load break fused switch as shown in Figure 1.1-30 or utilizing three on-off switches or a four-position sectionalizing
switch and vacuum fault interrupter (VFI) internal to the transformer saving
cost and reducing footprint.
When pad-mounted compartmentalized transformers
are used, they are furnished with loop-feed oil immersed gangoperated load
break sectionalizing switches and Bay-O-Net expulsion fuses in series with
partial range back-up current-limiting fuses. By operating the appropriate
sectionalizing switches, it is possible to disconnect any section of the loop
conductors from the rest of the system. In addition, it is possible to disconnect
any transformer from the loop.
Figure 1.1-29. Loop Primary—Radial Secondary System |
Figure
1.1-30. Secondary Unit Substation Loop Switching
|
Figure
1.1-31. VFI / Selector Switch Combination
|
Figure
1.1-32. Pad-Mounted Transformer Loop Switching
|
Figure
1.1-33. Basic Primary Selective—Radial Secondary System
|
A
key interlocking scheme is normally recommended to prevent closing all sectionalizing
devices in the loop. Each primary loop sectionalizing switch and the feeder
breakers to the loop are interlocked such that to be closed they require a key
(which is held captive until the switch or breaker is opened) and one less key
than the number of key interlock cylinders is furnished. An extra key is provided
to defeat the interlock under qualified supervision.
In addition, the two
primary main breakers, which are normally closed, and primary tie breaker,
which is normally open, are either mechanically or electrically interlocked to
prevent paralleling the incoming source lines. For slightly added cost, an
automatic throw-over scheme can be added between the two main breakers and tie breaker.
During the more common event of a utility outage, the automatic transfer scheme
provides significantly reduced power outage time.
The system in Figure
1.1-29 has higher costs than in Figure 1.1-28, but offers increased
reliability and quick restoration of service when
1)
a utility outage occurs,
2)
a primary feeder conductor fault occurs, or
3)
a transformer fault or overload occurs.
Should
a utility outage occur on one of the incoming lines, the associated primary
main breaker is opened and the tie breaker closed either manually or through an
automatic transfer scheme. When a primary feeder conductor fault occurs, the
associated loop feeder breaker opens and interrupts service to all loads up to
the normally open primary loop load break switch (typically half of the loads).
Once it is determined which section of primary cable has been faulted, the loop
sectionalizing switches on each side of the faulted conductor can be opened,
the loop sectionalizing switch that had been previously left open can then be
closed to all secondary unit substations while the faulted conductor is
replaced. If the fault should occur in a conductor directly on the load side of
one of the loop feeder breakers, the loop feeder breaker is kept open after
tripping and the next load side loop sectionalizing switch manually opened so
that the faulted conductor can be sectionalized and replaced. Under this
condition, all secondary unit substations are supplied through the other loop
feeder circuit breaker, and thus all conductors around the loop must be sized
to carry the entire load connected to the loop. Where separable load break or
non-load break connectors are used, they too must be sized to handle the entire
load of the loop. Increasing the number of primary loops (two loops shown in Figure
1.1-33) will reduce the extent of the outage from a conductor fault, but
will also increase the system investment.
When
a transformer fault or overload occurs, the transformer primary fuses open, and
the transformer primary switch manually opened, disconnecting the transformer
from the loop, and leaving all other secondary unit substation loads unaffected.
A basic primary loop system that uses a single primary feeder breaker connected
directly to two loop feeder switches which in turn then feed the loop is shown
in Figure 1.1-34. In this basic system, the loop may be normally operated
with one of the loop sectionalizing switches open as described above or with
all loop sectionalizing switches closed. If a fault occurs in the basic primary
loop system, the single loop feeder breaker trips, and secondary loads are lost
until the faulted conductor is found and eliminated from the loop by opening
the appropriate loop sectionalizing switches and then reclosing the breaker.
No comments:
Post a Comment