Article 230 of the National Electrical Code: “covers service
conductors and equipment for the protection of services and their installation
requirements”. Figure 1.1-22 provides
the scope of pertinent references that apply to incoming service equipment.
These range from conductor types from overhead service utility drops to underground
utility feeds and their proper installation.
Parts V, VI and VII of Article 230
spell out the common requirements for lowvoltage service equipment <1000
Vac. These parts cover locations permitted, various marking requirements including
Section 230.66 that requires service equipment be listed and marked as Suitable
for Use as Service Equipment, (SUSE). Also included is Section 230.71, which
limits the number of incoming main service disconnects to a maximum of six.
Section
230.95 of this Article requires equipment ground fault protection for service
disconnect(s) 1000 A and above when applied on solidly grounded wye services,
where the phase to ground voltage exceeds 150 V.
Article 250 of the NEC
contains the requirements for grounding and bonding of electrical systems.
Specific details pertaining to grounding for the incoming service equipment
begin at Section 250.24.
These include application of the grounding electrode
conductor in Section 250.50 to its sizing in accordance with Table 250.66.
Requirements for bonding of service equipment begins in Section 250.90. Sizing
of the main bonding jumper and system bonding jumper are also covered in Table 250.102(C)(1).
A more in-depth discussion of ground fault protection can be found in Section 1.5
of this Design Guide.
Figure 1.1-22. Application Zones of 2014 NEC Articles Related to Incoming Utility Services |
The
NEC Article 230 does not specifically require that electrical service rooms be fire
rated rooms or that sprinklers be provided. However, survivability requirements
for fire pump disconnects in local building code requirements, in addition to
NEC Article 450 or additional utility specifications may require fire rated
rooms, particularly if mediumvoltage service is being supplied.
Space
allocation should be considered when laying out equipment in a service room. Both
low- and medium-voltage utility metering typically adds an additional equipment
structure, or structures, to an incoming service lineup. These are used to
accommodate the current transformers and potential taps or voltage transformers
necessary for the external utility revenue meter to calculate usage.
Article
110 of the NEC covers a broad range of requirements for electrical
installations. It includes provisions that govern the construction and spatial requirements
for egress, clearances and working space in rooms containing electrical
distribution and service equipment.
Table 1.1 4 includes combined tables
from NEC Article 110, showing the minimum “depth of the working space in the direction
of live parts” required in front and behind medium-voltage equipment and
low-voltage equipment.
Table 1.1-4. NEC Minimum Depth of Clear Working Space at Equipment |
Additional
work space may need to be allocated for OSHA required grounding practices,
prior to servicing deenergized medium-voltage equipment. As an example,
6-foot-long insulated hot sticks are typically used to keep personnel at a safe
distance, while applying portable ground cables. This procedure is utilized to
discharge any residual capacitive voltage present on cables terminating in a
medium-voltage transformer primary cable compartment or in the rear cable compartment
of medium voltage switchgear.
As
renewable energy or cogeneration is added, power systems are becoming more
complex and so too is their service interface for utility power. Many Public
Service Commissions have adopted Standard Interface Requirements (SIR) for
Distributed Energy Resources (DER) based on IEEE 1547. These are intended to
protect the utility system from user owned generation back feeding into a fault
or dead cable on the utility grid.
Utilities may have their own specifications and
tariffs for the interconnection of this Dispersed or Distributed Generation
(DG). These include capacity limitations and/or the addition of charges for the
“spinning reserves” they must keep on hand, should the user’s DG assets fail or
load increase.
Consequently, the design engineer must be aware that special
relaying protection may need to be included in the design. Also, additional
analysis of the utility tariffs and rate structures may be necessary to
validate the projected payback of participation in peak demand reduction
programs using owner-supplied generation.
No comments:
Post a Comment